GEBE ST MAARTEN BLACKOUT CAUSED BY OVERHEATING AND SMALL FIRE

$
0
0

GEBE gave an explanation of Friday’s widespread blackout that lasted approximately two hours for most consumers. The company said it had started with a transformer cable overheating.

“On May 15, 2015, at 11:32am, NV GEBE technicians detected smoke in the high tension room. This was caused by the overheating of a cable from a transformer,” a company press release read.

gebe st maarten news photos judith roumou

gebe st maarten news photos judith roumou

“Attempting to switch power to a second transformer failed, causing a total blackout. Technicians managed to connect power to the alternate transformer and by 1:05pm more than 30 per cent was switched on. By 1:30pm all cables with the exception of Oyster Pond and Belvedere were back in service. At 1:45pm all cables were in full operation and working to full capacity.”

GEBE ST MAARTEN BLACKOUT CAUSED BY OVERHEATING AND SMALL FIRE


Filed under: GEBE ST MAARTEN BLACKOUT CAUSED BY OVERHEATING AND SMALL FIRE Tagged: GEBE ST MAARTEN BLACKOUT CAUSED BY OVERHEATING AND SMALL FIRE

Viewing all articles
Browse latest Browse all 2730

Latest Images

Trending Articles



Latest Images

<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>